Lucas Oil Stadium
Indianapolis, Indiana
We were in involved in placement of the Cast in Place Steps. The process involved using our program to ensure that each run was calculated individually to meet code of 3/16” tolerances. Scope involved pouring 2178 double steps and 1165 single steps, curb walls, surface tubs, layout and placement of rebar/ concrete.